[Hai’an Tianying] The first phase Hai’an MSW incineration power generation project
2014-06-25

        Under the proper leadership and careful organization by command dept, through solidarity close cooperation with all units, in Hai’an TY Environmental Protection Energy co., ltd, at 22:05 October 31, 2012, the first phase of waste incineration power project combined the grid successfully.
         During 1# generator unit trial operation, with stable operating conditions, parameters of the unit normal, instrument input rate, protection ratio, automatic device input rate of 100%, and excellent performance indicators meet the design requirements. From start to complete 72+24 hours at full load trial operation lasted 4 days, the realization of "ignition, turn, grid, 72+24 hours" four processes a success. In the process of construction of unit 1#, has completed the hydraulic test of boiler, steam turbine buckle cover, electric, electric power plant boiler ignition, steam turbine running, grid generation, 72+24 hours of trial operation, the seven key nodes successfully.
         Since 1# generator unit started trial operation, was paid more attentions by headquarter and project company, Project company leaders personally directed in command. Operation Department, technology department and other functional departments on-site gave supervision guidance, provided strong support for the entire transport, and greatly encouraged the cadres and staff morale. At the same time, in close cooperation with the Jiangxi electric item company in debugging, construction, supervision and other units, the establishment of trial operation command, overcome difficulties, elaborate organization and commission, to ensure that all work smoothly and orderly, the successful completion of the generator unit 1# realized from the infrastructure to smooth docking mission production.

友情链接: